If the handover date in your contract has passed and you still have no keys, you can claim a penalty for every day of delay, and if the delay is serious, terminate the contract and get your money back together with compensation for your losses. Below we explain how to check your contract, write a claim letter, where to complain and what to do if the case goes to court or the developer goes bankrupt.
Start with your documents, not with complaints. Almost everything that follows depends on what the contract says and how it was registered.
Shared construction is currently governed by Presidential Resolution PP-4732 of 27 May 2020 and the Regulation it approved. A separate law on shared construction with escrow accounts is still being considered by Parliament, so rely on the Regulation, the Civil Code and the Law "On Protection of Consumer Rights".
If the contract sets a penalty, claim it under the contract. If there is none, or it is negligible, and you are buying the apartment for yourself rather than for business, you can rely on the Law "On Protection of Consumer Rights":
Which of these rules fits your contract depends on its wording, and the court has the final say. Besides the penalty, you can claim compensation for losses, such as the rent you pay while waiting, and for moral damage (Article 22 of the same law). Note that if a penalty is clearly disproportionate to the consequences of the breach, the court may reduce it (Article 326 of the Civil Code).
Example. Suppose an apartment costs 600 million soums, the contract sets a penalty of 0.1% per day, and the building is handed over 100 days late. The contractual penalty is 600,000 soums per day, or 60 million soums for the whole period. That is the amount you put in your claim letter.
A claim letter (pretenziya) is a written demand to the developer. A consumer does not always have to send one before going to court, but it is almost always worth it: it records the delay and your demands, and some developers agree to settle after receiving it.
Yes. A significant delay is a ground for termination. Under Article 382 of the Civil Code, a court can terminate a contract if the other party materially breaches it, and under Article 337, if the delay means performance is no longer of interest to you, you can refuse it and claim damages. The consumer protection law (Article 19) also lets you withdraw from the contract and claim damages when it becomes obvious that the work will not be completed on time.
The sequence matters. First send the developer a proposal to terminate the contract. You can go to court with this demand once the developer refuses or fails to reply within the period stated in your proposal, or, if no period was stated, within 30 days (Article 384 of the Civil Code). Until the money is returned, you can charge interest on it for the use of another person's funds (Article 327 of the Civil Code).
Before terminating, weigh your options honestly. If the building is almost finished, it may pay to wait for the apartment and collect the penalty. If construction has stopped and the developer is running out of money, waiting is risky.
If the claim letter does not work, go to the inter-district civil court. A consumer may sue where the developer is located, where the consumer lives or where the harm was caused (Article 29 of the consumer protection law). You can file online at my.sud.uz.
Individuals are exempt from state duty in lawsuits over violations of consumer rights (the same Article 29). The general limitation period is three years (Article 150 of the Civil Code).
What to attach to the claim:
While your claim letter is pending, you can also contact the bodies that supervise developers:
You can look up a developer and its project on the Shaffof Qurilish portal (dshk.shaffofqurilish.uz). A complaint to a government body is not a substitute for a lawsuit: only a court can award you money and a penalty, unless the developer pays voluntarily.
The Law "On Insolvency" has special rules for shared construction developers (Articles 190–193):
Once insolvency proceedings start, file your claim in the case on time. Missing deadlines can cost you your place in the queue.
You can write a simple claim letter with a penalty calculation yourself. But in some situations a mistake is expensive:
A lawyer handling real estate and construction disputes can review your contract, calculate your claims correctly and help you choose a strategy: negotiation, a lawsuit or participation in the bankruptcy case.
In short
- Check your contract: the handover date, the penalty clause and registration on the Ministry of Construction platform.
- Claim the contractual penalty; if there is none, rely on the consumer protection law. A court may reduce a clearly excessive penalty.
- Send a written claim letter with a calculation and keep proof that you sent it.
- To terminate through the court, first propose termination to the developer and wait up to 30 days for a reply.
- Consumers pay no state duty in such cases and can sue where they live, including online at my.sud.uz.
- If the developer goes bankrupt, buyers' claims rank second, ahead of other creditors.